NEW QUESTION 16
How many different time levels can be selected within one planning view?
- A. Only base time levels of the planning area
- B. All time levels available in the time profile
- C. All time levels available in the time profile, restricted by global configuration parameter
- D. Only time levels from the base planning level of selected key figures
Answer: C
NEW QUESTION 17
What are some of the available ABC segmentation methods in IBP? Note: There are 2 correct Answers to this question.
- A. By Number of Items (Sorted Average)
- B. By Pareto Principle (Sorted and Calculated Values)
- C. By Number of Items (Sorted Values)
- D. By Pareto Principle (Sorted and Cumulated %)
Answer: B,C
NEW QUESTION 18
Which of the following checks for master data and key figures does the Check Mode algorithm trigger?
Note: There are 3 correct Answers to this question.
- A. It checks whether the required planning level master data exists for a subset of input key figures.
- B. It checks whether the sourcing in the Production Source Item Master Data type exists.
- C. It checks whether the heuristic detects cycles formed by nodes (such as location products) in the supply chain network.
- D. It checks whether the location resource specified in the master data forms a cycle in the supply chain network.
- E. It checks whether the location products specified in the master data are connected by customer sourcing rules within the supply chain network.
Answer: A,C,E
NEW QUESTION 19
Which of the following functional areas are included in the out-of-the-box SAP Integrated Business Planning application for sales and operations? Note: There are 3 correct Answers to this question.
- A. Rough-cut supply planning
- B. Executive review
- C. Consensus demand planning
- D. Finite resource capacities planning
- E. Demand-driven materials requirement planning
Answer: A,B,C
NEW QUESTION 20
What is a prerequisite for modeling outsourced manufacturers with production capacity?
- A. Model target inventory and stocks at the outsourced location.
- B. Model production costs for internal and external production resources to model priority.
- C. Ensure that multiple modes of transportation are set up.
- D. Use production lead times and offsets to manage components at the outsourced location.
Answer: B
NEW QUESTION 21
Which of the following data can be tracked using a change-history-enabled key figure? Note: There are 3 correct Answers to this question.
- A. Scenario ID
- B. Reason code
- C. Modified date
- D. Attributes
- E. Key figure type
Answer: B,C,D
NEW QUESTION 22
While modeling for a large machine with high capital needs, you need it to run cost effectively with minimum utilization, even if it means producing more than demand. Which solution would apply to this scenario? Note:
There are 2 correct Answers to this question.
- A. Capacity leveling will be possible for production and storage resources.
- B. Enough demands can be pulled forward and pull production will occur.
- C. Excess stock can be generated and will need to be staged in an overflow warehouse.
- D. Balance can be achieved between excessive prebuild and minimum utilization by incorporating violation costs.
Answer: B,D
NEW QUESTION 23
You are creating advanced copy operators as part of an SAP IBP solution that is being implemented.
What do you need to be aware of when defining data transfer? Note: There are 2 correct Answers to this question.
- A. Selecting by attribute with option 'contain' is possible.
- B. Specifying target key figure that is time independent is possible.
- C. Specifying target key figure is mandatory.
- D. Specifying source key figure is mandatory.
Answer: C,D
NEW QUESTION 24
You are working to realign the data due to a recent warehouse closure. What should you be aware of in regards to configuration of realignment steps? Note: There are 2 correct Answers to this question.
- A. If a realignment step fails, subsequent steps are not processed.
- B. The name of the realignment step should be no longer than 20 characters.
- C. The number of steps in realignment run is limited to 255.
- D. The realignment step status must be set to In Review for it to be executed.
Answer: A,D
NEW QUESTION 25
Which SAP IBP planning operator can be run to delete planning objects in a certain version?
- A. Purge Master Data
- B. Purge Key Figure Data Outside Planning Area Planning Horizon
- C. Purge Key Figure Data
- D. Purge Non-Confirming Data
Answer: C
NEW QUESTION 26
Which header name displays are available in the Report Options menu of the SAP IBP Excel interface?Note:
There are 2 correct Answers to this question.
- A. Business meaning, as defined in configuration
- B. Full unique name including the dimension and technical name
- C. Caption, as defined in configuration for the default name
- D. Changed member names that the user had created
Answer: A,B
NEW QUESTION 27
Which of the following are functions of SAP IBP for demand? Note: There are 3 correct Answers to this question.
- A. Embedded, on-the-fly demand analytics
- B. Demand sensing of demand data using the supply chain algorithm library
- C. Detailed statistical analysis of demand data using predictive analytics tools
- D. Demand sensing of demand data using predictive analytics tools
- E. Detailed statistical analysis of demand data using the supply chain algorithm library
Answer: A,B,E
NEW QUESTION 28
You are working with the inventory optimization process and you want to use a what-if analysis. What parameters are assessed by this analysis? Note: There are 2 correct Answers to this question.
- A. Number of planning combinations
- B. Capacity consumption
- C. Service levels
- D. Changed variability
Answer: C,D
NEW QUESTION 29
SAP is transitioning IBP customers to the new process of export/import. What are some of the features of this new process? Note: There are 2 correct Answers to this question.
- A. You can export from a planning area that is on a different release.
- B. You can choose to import only some of the items that were exported.
- C. You can move a transported item from one collection to another.
- D. You can create a collection of items and export it.
Answer: A,C
NEW QUESTION 30
You want to restrict value entries outside of a specified range into a key figure. What setting will you use to achieve that goal?
- A. Select Protect Active Worksheet in the About section of SAP IBP tab
- B. IBP -> Lock Selected cells in IBP Formatting Sheet tab
- C. By restricting data input in the Key Figure Configuration app
- D. IBP -> Data Validation in IBP Formatting Sheet tab
Answer: C
NEW QUESTION 31
What setting is mandatory in the Manage Lifecycle Planning app when introducing a new product?
- A. Define which phase-in and phase-out profiles can be used within Lifecycle Planning
- B. Define which is the attribute ID for the Lifecycle profiles
- C. Define at least one attribute of the planning area which represents the Product ID
- D. Define which key figure can be used as sales history for new products
Answer: D
NEW QUESTION 32
While modeling for a large machine with high capital needs, you need it to run cost effectively with minimum utilization, even if it means producing more than demand. Which solution would apply to this scenario? Note: There are 2 correct Answers to this question.
- A. Capacity leveling will be possible for production and storage resources.
- B. Enough demands can be pulled forward and pull production will occur.
- C. Excess stock can be generated and will need to be staged in an overflow warehouse.
- D. Balance can be achieved between excessive prebuild and minimum utilization by incorporating violation costs.
Answer: B,D
NEW QUESTION 33
......
Get 2022 Updated Free SAP C_IBP_2111 Exam Questions and Answer: https://www.actualpdf.com/C_IBP_2111_exam-dumps.html