NEW QUESTION # 31
Plugins may be added to the base platform in one of the following ways: (Choose three.)
- A. Activated by default in the base ServiceNow system.
- B. Activated by an it_portfolio_manager.
- C. Activated by an admin (not by default).
- D. Activated by an it_pps_admin.
- E. Requested from ServiceNow.
Answer: A,C,E
NEW QUESTION # 32
What system role is needed to manage programs?
- A. it_project_manager
- B. it_program_manager
- C. it_program_manager_admin
- D. it_portfolio_manager_admin
Answer: B
NEW QUESTION # 33
When can a user choose from multiple rate types for their work, while logging a time card?
- A. Only if the capability is enabled in the Project Preferences
- B. Only if this capability is enabled in the Project Record
- C. Only if the capability is enabled in the Time Sheet Policies
- D. Only one (1) rate type can apply
Answer: C
NEW QUESTION # 34
An it_pps_admin user is able to update: (Choose two.)
- A. Client Scripts.
- B. Portfolio Targets.
- C. Business Rules.
- D. Budget Periods.
Answer: B,D
NEW QUESTION # 35
This should be updated by an it_pps_admin, so that the stakeholder list will automatically populate when a user creates a demand or project.
- A. Project form.
- B. Application registry.
- C. Stakeholder registry.
- D. Demand form.
Answer: C
NEW QUESTION # 36
In what way would you restrict the assigned to field on a project task to only allow users with resource allocations to be assigned?
- A. Create a reference qualifier on the 'assigned to' field.
- B. On the project record under the preferences tab select the "Derive assignee list from resource plan" preference.
- C. Create an Access Control List (ACL) rule.
- D. The system automatically does this and can only be disabled by an admin.
Answer: B
NEW QUESTION # 37
Demand managers can enhance a demand request by adding the following: (Choose three.)
- A. Stakeholders
- B. Problems
- C. Decisions
- D. Requirements
- E. Change Requests
Answer: A,C,D
NEW QUESTION # 38
What is the demand workbench used for? (Choose two.)
- A. Comparing and prioritizing demands against other demands.
- B. Approving demands.
- C. Displaying submitted demands to stakeholders.
- D. Comparing demands with portfolios.
Answer: A,C
NEW QUESTION # 39
Which capability allows users to view variances in a project's schedule?
- A. Move project
- B. Project Status Report
- C. Machine-learning algorithms
- D. Compare scheduled baselines
Answer: D
NEW QUESTION # 40
Where can a user export project data in either a MPP, XML or CSV format?
- A. Related lists
- B. Planning Console
- C. Project Workbench
- D. Demand Form
Answer: B
NEW QUESTION # 41
To use the Time Sheet dashboard, what plugin must be installed?
- A. Employee Service Center (com.sn_hr_service_portal)
- B. Knowledge Management - Service Portal (com.snc.knowledge_serviceportal)
- C. Common ITSM Service Portal Application Components (com.snc.app_common.service_portal)
- D. Performance Analytics - Content Pack - PPM Standard plugin (com.snc.pa.pmo_dashboards)
Answer: D
NEW QUESTION # 42
In order for a business unit to have its own Idea Portal to retrieve data, what must be configured first?
- A. A business unit cannot have its own its own Idea Portal
- B. Idea categories
- C. Idea module
- D. Idea Portal URL
Answer: C
NEW QUESTION # 43
The Project Portfolio Management application supports domain separation at this level:
- A. Level 1 - Tenant data management
- B. Level 2 - Tenant process management
- C. Data only
- D. Level 3 - Tenant self-managed configuration
Answer: C
NEW QUESTION # 44
A customer requires five (5) teamspaces to support different departments. What should you do?
- A. Enable the teamspace property.
- B. Contact the Account Representative to activate the teamspaces.
- C. Use UI Policies and Business Rules to enable teamspaces.
- D. Activate via each teamspace plugin.
Answer: D
NEW QUESTION # 45
Which role can configure the parameters of the demand workbench that is provided with the base system?
- A. it_project_manager
- B. it_pps_admin.
- C. All roles.
- D. business_stakeholder.
Answer: B
NEW QUESTION # 46
Who can submit Ideas?
- A. Any ITIL user.
- B. Any IT user.
- C. Any demand user.
- D. Any user.
Answer: D
NEW QUESTION # 47
What applications are shared across teamspaces?
- A. Resource, Agile, Test
- B. Resource, Project Financials, Agile
- C. Agile, Test only.
- D. Project Financials, Agile, Test.
Answer: A
NEW QUESTION # 48
Which plugin activates the ideas module to gather and evaluate ideas efficiently, and quickly identify ideas for implementation?
- A. Test Management 2.0
- B. Resource Management
- C. Agile Development 2.0
- D. Ideation with PPM
Answer: B
NEW QUESTION # 49
Which of the following are true regarding how the My Project Space (Project Workspace) handles dynamic content? (Choose two.)
- A. If the project state is Work in Progress, actual start date and planned end date are displayed.
- B. If the project state is On Hold, actual start date and actual end date are displayed.
- C. If the project state is Draft, actual start date and actual end date are displayed.
- D. If the project state is Pending or Open, planned start date and planned end date are displayed.
Answer: A,D
NEW QUESTION # 50
What is the difference between confirm and allocate actions?
- A. They function the same way.
- B. Confirm action creates hard allocation and allocate action creates soft allocation.
- C. Confirm action creates soft allocation and allocate action creates hard allocation.
- D. Allocate action is always followed by confirm action.
Answer: C
NEW QUESTION # 51
What happens to the expense line after it is processed?
- A. The actual cost is recorded at the portfolio level.
- B. The cost plan closes.
- C. The actual amount incurred becomes part of the cost plan.
- D. Nothing significant results.
Answer: C
NEW QUESTION # 52
Which roles can modify agile properties? (Choose two.)
- A. scrum_master.
- B. it_pps_admin.
- C. admin.
- D. product_owner.
Answer: B,C
NEW QUESTION # 53
When creating a resource plan within a demand, how are the default dates on a resource plan determined?
- A. Resource plan(s) cannot be created from demand
- B. From portfolio date
- C. From demand start date and due date
- D. Using demand created date
Answer: C
NEW QUESTION # 54
Which of these tools allow you pinpoint over-allocated resources by viewing their negative availability values? (Choose two.)
- A. Resource Allocation Workbench
- B. Resource Reports
- C. Project Workbench
- D. Resource Plan Logs
Answer: A,B