NEW QUESTION 88
Reliability prediction is
I. The process of performance estimation.
II. The process of estimating the probability that a product will perform its intended function for a stated time.
III. The process of telling "how you can get there from here".
- A. I only
- B. I, II and III
- C. II only
- D. II and III only
Answer: C
NEW QUESTION 89
Typically Pareto diagrams are used for which of the following reasons?
I. To display the significant few categories.
II. To compliment attribute data charting.
III. To eliminate insignificant categories.
IV. To focus attention in priority order.
- A. I and III only
- B. II, III and IV only
- C. I, II, III and IV
- D. I, II and III only
Answer: C
NEW QUESTION 90
An electronics firm was experiencing high rejections in their multiple connector manufacturing departments. "p" charts were introduced as part of a program to reduce defectives. Control limits were based on prior history, using the formula:
P' is the historical value of percent defective and n is the number of pieces inspected each week. After six weeks, the following record was accumulated
1,000 pieces were inspected each week in each department. Which department(s) exhibited a point or points out of control during this period (round off calculations to nearest tenth of a percentage point)?
- A. Department 105.
- B. All of the department.
- C. Department 106.
- D. Department 104.
Answer: B
NEW QUESTION 91
A graph of a data set, composed of a series of rectangles, each proportional in width to the range of values in a class and proportional in height to the number of items or fraction of items falling in these classes, is called which of the following?
- A. Venn diagram.
- B. Histogram.
- C. Ogive.
- D. Raw data.
Answer: B
NEW QUESTION 92
Of the problem solving categories below, what is the usual sequence?
1. Select a problem needing improvement.
2. Collect data.
3. Implement the solution.
4. Determine if project is appropriate.
5. Study current procedures.
6. Determine candidates for data collection.
7. Analyze data.
8. Solve the problem.
- A. 1, 5, 6, 2, 4, 8, 7, 3
- B. 1, 5, 4, 6, 2, 7, 8, 3
- C. 4, 1, 5, 6, 2, 7, 8, 3
- D. 1, 4, 5, 6, 3, 8, 2, 7
Answer: B
NEW QUESTION 93
A system was designed with 3 capacitors. When the system is first activated all capacitors are operating. The system continues to operate as long as at least 1 capacitor is operating. This is an example of
- A. An active parallel system.
- B. A standby parallel system.
- C. Redundancy.
- D. A series system.
Answer: A
NEW QUESTION 94
Determine the coefficient of variation for the last 500 pilot plant test runs of high temperature film having a mean of 900 Kelvin with a standard deviation of 54.
- A. 6%
- B. 60%
- C. 16.7%
- D. 31%
Answer: A
Explanation:
Explanation/Reference:
Explanation:
% Coefficient of Variation = S/ (X-bar) * 100
54/ 900 * 100 = 6%
NEW QUESTION 95
If a distribution is skewed to the left, the median will always be
- A. Greater than the mode.
- B. Between the mean and the mode.
- C. Less than the mean.
- D. An average of the mean and the mode.
Answer: B
NEW QUESTION 96
Which of the following is NOT considered a prevention cost?
- A. Writing operating procedures.
- B. Data acquisition and analysis.
- C. Training.
- D. Calibrating test equipment.
Answer: D
NEW QUESTION 97
Which of the following are the MOST logical reasons for providing source inspection?
. The supplier has consistently shown poor out-going quality.
. The key inspection points are hidden after assembly at the suppliers' plant.
. The supplier requests the inspection to save them potential shipping expenses.
. The criticality of the product warrants it.
- A. IIandIVonly
- B. I,II,IIIandIV
- C. I,IIandIVonly
- D. II,IIIandIVonly
Answer: B
NEW QUESTION 98
A pre-award evaluation of a supplier's quality system capability should NOT include consideration of
- A. The supplier's product-quality history.
- B. The supplier's geographical location.
- C. The supplier's skills in quality control techniques.
- D. The supplier's implementation of quality manual procedures.
Answer: B
NEW QUESTION 99
A product failure in the customer's hands is bad for the company. Why do only 4% of the customers normally file a complaint?
- A. A warranty is in place on the product.
- B. The product guarantee takes care of the product.
- C. They don't think it will do any good.
- D. It is a minor inconvenience.
Answer: C
NEW QUESTION 100
The term "quality audit" can refer to the appraisal of the quality system of
. An entire plant or company.
. One product.
. One major quality activity.
- A. I andIIIonly
- B. I only
- C. IIandIIIonly
- D. I,IIandIII
Answer: D
NEW QUESTION 101
Measurement gaging is preferable to go, no-go gaging of a quality characteristic because
- A. It requires a larger sample than go, no-go gaging does.
- B. It provides the most information per piece inspected.
- C. It requires greater skills.
- D. It is more scientific.
Answer: B
NEW QUESTION 102
A box contains 27 black and 3 red balls. A random sample of 5 balls is drawn without replacement. What is the probability that the sample contains one red ball?
- A. 0.108
- B. 0.500
- C. 0.369
- D. 0.270
Answer: C
NEW QUESTION 103
One-way analysis of variance is MOST similar in its objectives to
- A. A chi-square test for independence.
- B. A test for equality of two population means.
- C. A test for equality of two sample proportions.
- D. A test of a population mean.
Answer: B
NEW QUESTION 104
Which of the following quality gurus was very critical of merit-pay and individual bonuses?
He discouraged management by objectives and the ranking of employees by performance.
- A. Dr. Feigenbaum
- B. Dr. Deming
- C. Dr. Taguchi
- D. Dr. Juran
Answer: B
NEW QUESTION 105
The sample size for a product quality audit should be
- A. Based on ANSI/ASQ Z1.4.
- B. A very small quantity of product.
- C. A stated percentage of production.
- D. Based on the lot size.
Answer: B
NEW QUESTION 106
A purchase order for subassemblies classified as critical must include a review by
. Quality engineering.
. The procurement department.
. Design engineering.
- A. I andIIIonly
- B. IIandIIIonly
- C. I,IIandIII
- D. IIIonly
Answer: C
NEW QUESTION 107
What is the lower control limit for proportion defective if the average daily production is 5000 units and the average fraction defective is 0.02?
- A. 0.016
- B. 0.010
- C. 0.014
- D. 0
Answer: C
NEW QUESTION 108
......
Ultimate Guide to Prepare CQE Certification Exam for ASQ Certification: https://www.actualpdf.com/CQE_exam-dumps.html
Use Real CQE Dumps - ASQ Correct Answers: https://drive.google.com/open?id=146cus9MxpfiLDyk1OpaiaF5eEZaUOG0F